Target Distribution Center ($10.5M)

Contract Amount: $10.5 Million

Target Distribution Center is a 100 acre development site with a 1,500,000 square foot distribution center under one roof along with more than 50 acres of tractor trailer parking. R.B. Baker Construction was awarded this $10.5 project in 2007 and the scope of work included clearing, mass grading (in excess of 300,000 cubic yards of material moved), 23,000 linear feet of wet utilities (storm, water, and sewer), 230,000 square yards of graded aggregate base, 21,000 linear feet of concrete curb, and 47,000 tons of asphalt paving.